Country | Investor | Facility | Equipment | Capacity kt | Capex $m |
Argentina | ArcelorMittal | Acindar | Wind power | 76.5 MW | 140 |
Austria | VoestAlpine | Linz | Pickling line [flat] | 2000 | 214 |
Belgium | ArcelorMittal | Ghent | Desulphurisation | n/a | n/a |
Bolivia | Aceros Arequipa | Lat Am Indust Park i | ERW pipe | 60 | 20 |
Brazil | Sinobras | Sinobras | Bar mill | 500 | 203 |
USA | Nucor | Nucor Steel Gallatin | Structural sections | 226 | 164 |
USA | Nucor | Not disclosed | Micro mill | 390 | 350 |
USA | US Steel | Big River, Arkansas | Electrical steel | 180 | 450 |
USA | US Steel | Gary Works | Pig iron caster | 450 | 60 |
Vietnam | Kyoei Steel | Vietnam Italy Steel | Bar mill | 500 | 80 |
Number of capital investment records shown: 10
Subscribers get access to 38 capex cost records.
Click here to subscribe.
All investment and modernisation projects above are scheduled for commissioning in year 2023. Capacity data is expressed in metric tonnes.
MCI holds a database of over 1050 steel industry modernisation projects. This database contains individual modernisation records identifying the country, investor, facility, capacity impact, capital cost, capex cost per tonne, commissioning date etc. Please email info@steelonthenet.com
or call +44 775 149 0885 for further information.
Looking to improve your plant's operating performance? We have technical experts in melting casting and rolling, who are able to diagnose problems and offer recommendations. See our case studies page.